Kicking Horse widening budget up $151 million as bidders invited

Union-only construction adds 5.8% to price of B.C.’s toughest project

B.C.’s transportation ministry is inviting bids to design and build the most difficult highway project in the province’s history, with costs going up, mainly due to union-only construction and engineering changes.

The latest cost estimate for the fourth phase of the Kicking Horse Canyon widening project is $601 million, a $151 million increase since the 2016 project budget. The ministry estimates that $35 million of that is to implement the NDP government’s “community benefits agreement” for public construction projects, requiring worker membership in approved building trades unions.

Other increased costs include additional geotechnical and other engineering work, additional foundation supports for bridges and retaining walls, consultation with Indigenous communities and a bigger contingency fund due to the risk and complexity of the project.

Phase four is four-laning of the final section of Kicking Horse Canyon east of Golden, 4.8 km from West Portal to Yoho Bridge. Construction is slated to begin in the summer of 2020, with completion by the winter of 2023-24.

The cost increase also includes an additional $23 million in interest charges, since the project was initially approved with a $450 million price tag in 2015.

Transportation Minister Claire Trevena emphasized the safety improvement needed in the Kicking Horse Canyon, which has an accident rate three times the average for B.C. highways and areas with effectively no shoulder for vehicles to pull off in an emergency.

RELATED: B.C. Highway 1 widening demanded for decades

RELATED: Single-bridge option chosen for Sicamous section

The average speed for the existing canyon road is 55-65 km/h, causing long backups behind transport trucks and recreational vehicles winding through the scenic route. The objective of the widening is to get the average speed up to 100 km/h as well as enhance safety.

The project will require closure of the Trans Canada Highway from Castle Junction to Golden for an estimated total of 15 weeks. A detour route using Highway 93 and 95 through Radium Hot Springs will add 104 km to the route, approximately an hour and a half of additional travel time.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

Just Posted

Cranbrook council, staff tweak funding sources for industrial land development

Discussions over funding industrial development continues in preparation of five-year financial plan

Selby’s ‘Freedom Libraries’ hits the shelves

Childhood movie revelation led to the writing of a ‘Freedom Libraries: The Untold Story of Libraries for African Americans in the South.’

Regional winter road maintenance operations underway

Mainroad East Kootenay Contracting shifting into winter as snow season fast approaches

Columbia River Treaty: ‘It is going to get tough’

B.C. negotiator tells Nelson meeting that talks are cordial, so far

WildSafeBC reminds East Kootenay residents to give deer space during rut

Be cautious when driving as well, says WildSafeBC

VIDEO: ‘Climate emergency’ is Oxford’s 2019 Word of the Year

Other words on the shortlist included ‘extinction,’ ‘climate denial’ and ‘eco-anxiety’

65-million-year-old triceratops makes its debut in Victoria

Dino Lab Inc. is excavating the fossilized remains of a 65-million-year-old dinosaur

B.C. widow suing health authority after ‘untreatable’ superbug killed her husband

New Public Agency Health report puts Canadian death toll at 5,400 in 2018

Changes to B.C. building code address secondary suites, energy efficiency

Housing Minister Selina Robinson says the changes will help create more affordable housing

Security guard at Kamloops music festival gets three years for sexually assaulting concertgoer

Shawn Christopher Gray walked the woman home after she became seperated from her friends, court heard

Algae bloom killing farmed fish on Vancouver Island’s West Coast

DFO says four Cermaq Canada salmon farms affected, fish not infectious

Three cops investigated in connection to ex-Vancouver detective’s sexual misconduct

Fisher was convicted in 2018 after pleading guilty to kissing two young women who were witnesses in a criminal case

Most Read